Skip To Main Content
Edmonds School District

Latest Project Updates

News updates for all Capital Projects related work will be posted here. Check back for updates!

RSS   Add this page to your favorite RSS reader to be notified when updates are posted.   RSS

The Mountlake Terrace High School HVAC Project reached substantial completion on 8/29/2025. The system is currently undergoing testing and balancing, as well as final commissioning. Over the next year the system will continue to be tuned to run smoothly and efficiently, increasing comfort for students and staff, reducing the operational noise of the system and reducing the building’s energy consumption.

The geothermal well drilling and all roofing work have been completed. As part of the ongoing project, a new synthetic turf field will be installed. This is an exciting addition that will support students’ passion for soccer and serve the broader needs of the community. The undercover play area is erected and the finishing touches being finalised. Construction across all areas continues to progress according to schedule.

Oak Heights Elementary

View from the gym to the commons, showcasing the beautiful glulam beams.

Oak Heights Elementary

View of skybridge and undercover walkway, with ADA access between the levels.

College Place Elementary and Middle School has reached 50% Construction Documentation and SEPA has been approved. The project is currently in the Project Design Review (PDR) process with the City of Lynnwood. The District has enjoyed partnering with the City through this process. The purpose for the PDR is to ensure high-quality development by complying with Lynnwood Citywide Design Guidelines and all relevant codes and ordinances, while coordinating with nearby private developments and public improvement projects in the area.

The Fieldhouse project has the beginnings of a roof and temporary bracing of the side walls have been removed! Steel trusses are in, roof decking has been completed, and storefront windows have recently arrived on site for installation. The first concrete pour at the south side of the building shows a preview of what the adjacent plaza will look like. Plumbing & electrical are also underway, with preparation for mechanical systems occurring in the coming weeks.

EWH Fieldhouse
EWH Fieldhouse
EWH Fieldhouse
EWH Fieldhouse

Construction across all areas is progressing steadily. Wall painting and installation of casework, ceiling grids, doors, and sheet metal flashing are underway, while the steel skybridge connecting the classroom wings is structurally complete and concrete has been poured. The public wing has seen MEP rough-ins, drywall finishing, exterior cladding, skylight installations, and canopy erection, with the ground-level concrete walkway poured. Roadwork on 18th Ave and Oak Road is complete, fencing has been installed, and preparations for landscaping have begun. Sidewalk and curb concrete work was ready for students to access the bus for the start of school, and geothermal well drilling and pipe installation are almost complete.

OHE

Looking across the skybridge

OHE

Looking east, from the library

OHE

South facade of classroom wing

Brier Elementary and Martha Lake Elementary Schools have a new roof structure to cover the existing outdoor play space. The project consisted of a new unenclosed steel roof structure, new basketball hoops and new painted courts for a variety of play activities. Thank you to our voters for another successful project funded by 2021 Capital Levy which was completed on time and under budget.

Covered Playshed Project at Brier Elementary and Martha Lake Elementary
Covered Playshed Project at Brier Elementary and Martha Lake Elementary

The new 5,000-square-foot facility is under construction on the Edmonds-Woodway High School campus, between the football stadium and the baseball field, on the site of the former tennis courts. The fieldhouse will serve as a multipurpose space, providing an auxiliary gym as well as concessions and restroom facilities for the surrounding athletic fields and tennis courts.

Edmonds-Woodway High School Multipurpose Fieldhouse
Edmonds-Woodway High School Multipurpose Fieldhouse