Skip To Main Content
Edmonds School District

Oak Heights Elementary Project Updates

Oak Heights Elementary Update for December 9

Oak Height Elementary School's construction continues to progress according to schedule. All geothermal drilling has been completed. Site activities run concurrently, covering drainage and rock placement for the playground and field, turf field delivery and installation, plus continued work on site concrete, electrical infrastructure, and irrigation/landscaping are taking place. Other exterior building work includes sheet metal flashing, siding, brick installation, and window and door frame installation.

Interior tasks focus on installing tackable wall surfaces, ceramic tile, wood wall panels, hallway acoustical ceiling panels, and completing MEP trim, framing, drywall hanging, taping, and miscellaneous painting.

Oak Heights Elementary
Oak Heights Elementary Update for October 16, 2025

The geothermal well drilling and all roofing work have been completed. As part of the ongoing project, a new synthetic turf field will be installed. This is an exciting addition that will support students’ passion for soccer and serve the broader needs of the community. The undercover play area is erected and the finishing touches being finalised. Construction across all areas continues to progress according to schedule.

Oak Heights Elementary

View from the gym to the commons, showcasing the beautiful glulam beams.

Oak Heights Elementary

View of skybridge and undercover walkway, with ADA access between the levels.

Oak Heights Elementary September 29 Update

Construction across all areas is progressing steadily. Wall painting and installation of casework, ceiling grids, doors, and sheet metal flashing are underway, while the steel skybridge connecting the classroom wings is structurally complete and concrete has been poured. The public wing has seen MEP rough-ins, drywall finishing, exterior cladding, skylight installations, and canopy erection, with the ground-level concrete walkway poured. Roadwork on 18th Ave and Oak Road is complete, fencing has been installed, and preparations for landscaping have begun. Sidewalk and curb concrete work was ready for students to access the bus for the start of school, and geothermal well drilling and pipe installation are almost complete.

OHE

Looking across the skybridge

OHE

Looking east, from the library

OHE

South facade of classroom wing