Oak Heights Elementary Project Updates
Installation of new accessible playground is underway.

Looking across the new artificial turf, cork infill playfield, toward the classroom wings.

The Kindergarten play area and trike track have their own area directly outside of the classrooms.

Typical classrooms with casework and a calmdown zone are almost complete.

Typical undercover porch outside of every classroom on the ground level. This area is within the secure perimeter of the building and has door access and visual connectivity to the classroom.

Cedar timber brings the feeling of calm and warmth to the undercover areas.

The split level atrium, thoroughfare, stairs and learning nooks are coming together with final touches.

The final stages of construction at Oak Height Elementary School are taking place and progressing according to schedule. The artificial turf field is fully installed and ready to welcome students when school opens. Playground equipment is being installed and the finished concrete in the gym was poured and is now curing. The gym floor installation is scheduled for the end of February.
Concrete pours in the commons and exterior concrete for landscaping and playground areas have been successful. Landscaping is now ready to receive topsoil. Mechanical system activities are being finalised and building commissioning continues.




Construction at Oak Height Elementary School continues to progress according to schedule. The artificial turf field has been installed, and playground and gym floor installation is scheduled to begin at the end of January.
Ongoing work includes concrete pours in the commons as well as exterior concrete for landscaping and playground areas. Mechanical system activities are currently underway, including Dedicated Outdoor Air Systems (DOAS) installation and geothermal system testing. Building commissioning has also begun.






