List of Projects for Secondary Schools and Other Programs
Timeline: Capital Improvements Across the District
Did you know? Money from the 2006 Capital Construction Bond and from the sale or ground lease of district property legally must go toward capital improvements. It cannot help fund instruction or staffing needs.
*Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site.
Middle Schools
Alderwood Middle School
Location: 20000 28th Avenue W., Lynnwood
Funding Source |
Project Description |
Est. Completion Date* |
Revenue from Surplus Property |
Build new school facility |
TBD* |
2008 Technology/Capital Levy |
Technology: Replace equipment purchased by the 2004 Capital Levy, including projector, document presenter, and instructional laptop in each classroom; mobile computer lab equipment; computers in classrooms; and library circulation desk equipment. |
Ongoing |
2008 Technology/Capital Levy | Technology: Install additional mobile computer labs | Ongoing |
2008 Technology/Capital Levy | Technology: Create a new school website to improve communication with the public and develop an internal website to support staff needs | Ongoing |
2008 Technology/Capital Levy | Technology: Replace technology lab computers |
|
2006 Capital Construction Bond |
Install emergency storage structure |
|
2006 Capital Construction Bond |
Upgrade data cabling |
|
2004 Capital Levy |
Technology: Install a projector, document presenter, and instructional laptop in each classroom |
|
2004 Capital Levy |
Technology: Install mobile lab equipment |
|
2004 Capital Levy |
Technology: Install additional computers in classrooms |
|
2004 Capital Levy |
Upgrade science lab safety |
|
2004 Capital Levy |
Athletic fields: Add under-irrigation to football/soccer and baseball fields and irrigation to fastpitch field |
|
2004 Capital Levy |
Install asphalt and all-weather surface to runway and high-jump areas |
|
*Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site. |
Brier Terrace Middle School
Location: 22200 Brier Road, Brier
Funding Source |
Project Description |
Est. Completion Date* |
2008 Technology/Capital Levy |
Technology: Replace equipment purchased by the 2004 Capital Levy, including projector, document presenter, and instructional laptop in each classroom; mobile computer lab equipment; computers in classrooms; and library circulation desk equipment. |
Ongoing |
2008 Technology/Capital Levy | Technology: Install additional mobile computer labs | Ongoing |
2008 Technology/Capital Levy | Technology: Create a new school website to improve communication with the public and develop an internal website to support staff needs | Ongoing |
2008 Technology/Capital Levy | Technology: Replace technology lab computers |
|
2008 Technology/Capital Levy | Install HVAC digital control system to improve energy efficiency and improve our ability to maintain building temperatures | 2012 |
2006 Capital Construction Bond |
Install emergency storage structure |
|
2006 Capital Construction Bond |
Upgrade heating/ventilation controls |
|
2006 Capital Construction Bond |
Upgrade data cabling |
|
2006 Capital Construction Bond |
Replace moveable partitions in two classrooms |
2011 |
2004 Capital Levy |
Technology: Install a projector, document presenter, and instructional laptop in each classroom |
|
2004 Capital Levy |
Technology: Install mobile lab equipment |
|
2004 Capital Levy |
Technology: Install additional computers in classrooms |
|
2004 Capital Levy |
Upgrade science lab safety |
|
2004 Capital Levy |
Earthquake safety upgrades |
|
2004 Capital Levy |
Athletic fields: Add under-drainage and irrigation to football/soccer and baseball fields and irrigation to fastpitch field |
|
2004 Capital Levy |
|
|
*Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site. |
College Place Middle School
Location: 7501 208th Street SW, Lynnwood
Funding Source |
Project Description |
Est. Completion Date* |
2008 Technology/Capital Levy |
Technology: Replace equipment purchased by the 2004 Capital Levy, including projector, document presenter, and instructional laptop in each classroom; mobile computer lab equipment; computers in classrooms; and library circulation desk equipment. |
Ongoing |
2008 Technology/Capital Levy | Technology: Install additional mobile computer labs | Ongoing |
2008 Technology/Capital Levy | Technology: Create a new school website to improve communication with the public and develop an internal website to support staff needs | Ongoing |
2008 Technology/Capital Levy | Technology: Replace technology lab computers | Spring 2011 |
2008 Technology/Capital Levy | Install HVAC digital control system to improve energy efficiency and improve our ability to maintain building temperatures | 2012 |
2006 Capital Construction Bond |
Install emergency storage structure |
|
2006 Capital Construction Bond |
Upgrade data cabling |
|
2004 Capital Levy |
Technology: Install a projector, document presenter, and instructional laptop in each classroom |
|
2004 Capital Levy |
Technology: Install mobile lab equipment |
|
2004 Capital Levy |
Technology: Install additional computers in classrooms |
|
2004 Capital Levy |
Upgrade science lab safety |
|
2004 Capital Levy |
Earthquake safety upgrades |
|
2004 Capital Levy |
Athletic fields: Add under-drainage and irrigation to football/soccer and baseball fields and irrigation to fastpitch field |
|
2004 Capital Levy |
Install asphalt and all-weather surface to runway and high-jump areas |
|
*Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site. |
Meadowdale Middle School
Location: 6500 168th Street SW, Lynnwood
Funding Source |
Project Description |
Est. Completion Date* |
2008 Technology/Capital Levy |
Technology: Replace equipment purchased by the 2004 Capital Levy, including projector, document presenter, and instructional laptop in each classroom; mobile computer lab equipment; computers in classrooms; and library circulation desk equipment. |
Ongoing |
2008 Technology/Capital Levy | Technology: Install additional mobile computer labs | Ongoing |
2008 Technology/Capital Levy | Technology: Create a new school website to improve communication with the public and develop an internal website to support staff needs | Ongoing |
2008 Technology/Capital Levy | Technology: Replace technology lab computers | Summer 2011 |
2006 Capital Construction Bond |
Build new school facility |
Fall 2011 |
2006 Capital Construction Bond |
Install emergency storage structure |
|
2006 Capital Construction Bond |
Upgrade data cabling |
|
2004 Capital Levy |
Technology: Install a projector, document presenter, and instructional laptop in each classroom |
|
2004 Capital Levy |
Technology: Install mobile lab equipment |
|
2004 Capital Levy |
Technology: Install additional computers in classrooms |
|
2004 Capital Levy |
Upgrade science lab safety |
|
*Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site. |
High Schools
Edmonds-Woodway High School
Location: 7600 212th Street SW, Edmonds
Funding Source |
Project Description |
Est. Completion Date* |
2008 Technology/Capital Levy |
Technology: Replace equipment purchased by the 2004 Capital Levy, including projector, document presenter, and instructional laptop in each classroom; mobile computer lab equipment; computers in classrooms; and library circulation desk equipment. |
Ongoing |
2008 Technology/Capital Levy | Technology: Install additional mobile computer labs | Ongoing |
2008 Technology/Capital Levy | Technology: Create a new school website to improve communication with the public and develop an internal website to support staff needs | Ongoing |
2008 Technology/Capital Levy | Technology: Replace library computer labs |
|
2008 Technology/Capital Levy | Install roof protection anchor system | Summer 2011 |
2008 Technology/Capital Levy | Install CCTV system | 2011 |
2008 Technology/Capital Levy | Install HVAC digital control system to improve energy efficiency and improve our ability to maintain building temperatures |
|
2006 Capital Construction Bond |
|
|
2004 Capital Levy |
|
|
2004 Capital Levy |
|
|
2004 Capital Levy |
|
|
2004 Capital Levy |
|
|
2004 Capital Levy |
|
|
2004 Capital Levy |
|
Project Canceled |
2004 Capital Levy |
|
Project Canceled |
*Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site. |
Lynnwood High School
Location: 3001 184th Street SW, Lynnwood (current) -- 18217 North Road, Bothell (future)
Funding Source |
Project Description |
Est. Completion Date* |
2008 Technology/Capital Levy |
Technology: Replace equipment purchased by the 2004 Capital Levy, including projector, document presenter, and instructional laptop in each classroom; mobile computer lab equipment; computers in classrooms; and library circulation desk equipment. |
Ongoing |
2008 Technology/Capital Levy | Technology: Install additional mobile computer labs | Ongoing |
2008 Technology/Capital Levy | Technology: Create a new school website to improve communication with the public and develop an internal website to support staff needs | Ongoing |
2008 Technology/Capital Levy | Technology: Replace library computer labs |
|
2006 Capital Construction Bond |
Build new school facility |
|
2006 Capital Construction Bond |
Install emergency storage structure |
|
2004 Capital Levy |
Design new facility |
|
2004 Capital Levy |
Technology: Install a projector, document presenter, and instructional laptop in each classroom |
|
2004 Capital Levy |
Technology: Install mobile lab equipment |
|
2004 Capital Levy |
Technology: Install additional computers in classrooms |
|
2004 Capital Levy |
Resurface and paint track (partially funded by the City of Lynnwood) |
|
2004 Capital Levy |
Upgrade science lab safety |
|
*Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site. |
Meadowdale High School
Location: 6002 168th Street SW, Lynnwood
Funding Source |
Project Description |
Est. Completion Date* |
2008 Technology/Capital Levy |
Technology: Replace equipment purchased by the 2004 Capital Levy, including projector, document presenter, and instructional laptop in each classroom; mobile computer lab equipment; computers in classrooms; and library circulation desk equipment. |
Ongoing |
2008 Technology/Capital Levy | Technology: Install additional mobile computer labs | Ongoing |
2008 Technology/Capital Levy | Technology: Create a new school website to improve communication with the public and develop an internal website to support staff needs | Ongoing |
2008 Technology/Capital Levy | Technology: Replace library computer labs |
|
2008 Technology/Capital Levy | Install CCTV system | 2011 |
2008 Technology/Capital Levy | Install HVAC digital control system to improve energy efficiency and improve our ability to maintain building temperatures | 2012 |
2006 Capital Construction Bond |
Install emergency storage structure |
|
2006 Capital Construction Bond |
Eradicate Scotch broom |
|
2006 Capital Construction Bond |
Install one new fume hood |
|
2004 Capital Levy |
Technology: Install a projector, document presenter, and instructional laptop in each classroom |
|
2004 Capital Levy |
Technology: Install mobile lab equipment |
|
2004 Capital Levy |
Technology: Install additional computers in classrooms |
|
2004 Capital Levy |
Upgrade science lab safety |
|
2004 Capital Levy |
Install all-weather track |
|
2004 Capital Levy |
Capital Partnership Program: field renovations |
|
*Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site. |
Mountlake Terrace High School
Location: 21801 44th Avenue W, Mountlake Terrace
Funding Source |
Project Description |
Est. Completion Date* |
2008 Technology/Capital Levy |
Technology: Replace equipment purchased by the 2004 Capital Levy, including projector, document presenter, and instructional laptop in each classroom; mobile computer lab equipment; computers in classrooms; and library circulation desk equipment. |
Ongoing |
2008 Technology/Capital Levy | Technology: Install additional mobile computer labs | Ongoing |
2008 Technology/Capital Levy | Technology: Create a new school website to improve communication with the public and develop an internal website to support staff needs | Ongoing |
2008 Technology/Capital Levy | Technology: Replace library computer lab |
|
2008 Technology/Capital Levy | Replace carpet | Summer 2011 |
2008 Technology/Capital Levy | Replace gymnasium roof |
|
2008 Technology/Capital Levy | Install roof protection anchor system | Summer 2011 |
2008 Technology/Capital Levy | Install CCTV system | 2011 |
2008 Technology/Capital Levy | Install HVAC digital control system to improve energy efficiency and improve our ability to maintain building temperatures | 2011 |
2008 Technology/Capital Levy | Capital Partnership Program: Music storage area |
|
2006 Capital Construction Bond |
Install emergency storage structure |
|
2006 Capital Construction Bond |
Install two new fume hoods |
|
2006 Capital Construction Bond |
Replace stage flooring |
|
2004 Capital Levy |
Technology: Install a projector, document presenter, and instructional laptop in each classroom |
|
2004 Capital Levy |
Technology: Install mobile lab equipment |
|
2004 Capital Levy |
Technology: Install additional computers in classrooms |
|
2004 Capital Levy |
Upgrade data cabling |
|
2004 Capital Levy |
Upgrade science lab safety |
|
2004 Capital Levy |
Install FieldTurf to field and lights to tennis courts |
|
*Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site. |
Scriber Lake High (Alternative Learning Center)
Location: 23200 100th Ave. W, Edmonds (current) -- 20420 68th Avenue W, Lynnwood (future)
Funding Source |
Project Description |
Est. Completion Date* |
Revenue from Surplus Property |
Renovate existing ESC facility for classroom purposes |
TBD |
2008 Technology/Capital Levy |
Technology: Replace equipment purchased by the 2004 Capital Levy, including projector, document presenter, and instructional laptop in each classroom; mobile computer lab equipment; computers in classrooms; and library circulation desk equipment. |
Ongoing |
2008 Technology/Capital Levy | Technology: Install additional mobile computer labs | Ongoing |
2008 Technology/Capital Levy | Technology: Create a new school website to improve communication with the public and develop an internal website to support staff needs | Ongoing |
2008 Technology/Capital Levy | Technology: Replace library computer lab |
|
2008 Technology/Capital Levy | Install CCTV system | 2011 |
2008 Technology/Capital Levy | Install HVAC digital control system to improve energy efficiency and improve our ability to maintain building temperatures | 2011 |
2004 Capital Levy |
Design new facility |
|
2004 Capital Levy |
Technology: Install a projector, document presenter, and instructional laptop in each classroom |
|
2004 Capital Levy |
Technology: Install mobile lab equipment |
|
2004 Capital Levy |
Technology: Install additional computers in classrooms |
|
*Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site. |
Other Programs
Alderwood Early Childhood Center
Location: 2000 200th Place SW, Lynnwood (former Alderwood Elementary)
Funding Source |
Project Description |
Est. Completion Date * |
2008 Technology/Capital Levy | Technology: Replace schoolwide technology tools | Ongoing |
2008 Technology/Capital Levy | Technology: Create a new school website to improve communication with the public and develop an internal website to support staff needs | Ongoing |
2008 Technology/Capital Levy | Install HVAC digital control system to improve energy efficiency and improve our ability to maintain building temperatures | 2011 |
2006 Capital Construction Bond |
|
|
2004 Capital Levy |
|
|
2004 Capital Levy |
|
|
*Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site. |
Edmonds Heights K-12
Location: 23200 100th Avenue W, Edmonds (former Woodway High School)
Funding Source |
Project Description |
Est. Completion Date* |
2008 Technology/Capital Levy | Technology: Replace schoolwide technology tools | Ongoing |
2008 Technology/Capital Levy | Install CCTV system | 2011 |
2008 Technology/Capital Levy | Install HVAC digital control system to improve energy efficiency and improve our ability to maintain building temperatures | 2011 |
2008 Technology/Capital Levy | Capital Partnership Program: playground | 2011 |
2006 Capital Construction Bond |
|
|
2006 Capital Construction Bond |
|
|
2004 Capital Levy |
|
|
2004 Capital Levy |
|
|
2004 Capital Levy |
|
|
2004 Capital Levy |
|
|
*Please note: The Edmonds School District is committed to completing the capital improvement work at each school as outlined on this web site. However, all timelines are dependent on a variety of factors and are subject to change. Any changes will be updated as soon as possible on this web site. |