Fall 2008
School Takes Shape
Construction at the site of the new Lynnwood High School at 18218 North Road has been underway for more
than a year, and progress is impressive. Construction is divided into zones, which are built sequentially.
The large central "Agora" space and two classroom wings, first in the sequence, will soon have drywall
in place. The library/gymnasium wing is framed and fireproofed, and roofing is in progress. The theater/arts
wing is close to completion with roofing, and enclosure work will follow this winter.
During summer 2008, site work (roads, parking areas, and athletic fields) pushed much closer to completion. The baseball field
is almost done, and the football field's artificial turf will be placed this fall. In addition, road
right-of-way and sidewalk improvements are largely done, and the traffic signal on North Road is in place,
although not yet operation.
This project is funded by the voter-approved 2006 Bond and is expected to be complete in summer 2009
and operational for start of school in September.
For more information about the project, contact project manager Debra Born at 425-672-8174
or bornd@edmonds.wednet.edu.